Timeline

11 September 2012 – First visit to Metricon to look into the Franklin
12 September 2012 – Met with Sales Consultant in Rochedale to find out whether the Franklin was a suitable fit for our block, obtained price and special promotions and paid $1,500 deposit
16 September 2012 – Looked at actual Franklin on Display at North Lakes
18 September 2012 – Looked at display in Rochedale and went through floor plan in detail and items that were and were not included to get initial extra upgrades etc for preliminary contract to be drafted
22 September 2012 – first visit to Studio M and tile shop
22 October 2012 – Preliminary contract meeting and signing, paid a further $1,000 deposit
27 October 2012 – Second visit to Studio M and tile shop
27 November 2012 – Contract Signing! – and variation document (initial estimated start date 22.2.13)
….received a letter from Metricon advising us of our customer support co-ordinator
11 December 2012 – Received a copy of our signed contract
20 December 2012 – 5% deposit paid
7 January 2013 – Electrical Appointment and Tile Studio Appointment
8 January 2013 – Studio M Appointment
11 January 2013 – received electrical and tile variations
31 January 2013 – Received Studio M variations
21 February 2013 – Signed amended electrical and tile variations
27 February 2013 – Signed amended Studio M variations1

28 February 2013 – Final drawings were requested!

4 March 2013 – Audit of file in process

11 March 2013 – Splashback colour changed

12 March 2013 – Audit complete. A few discrepancies noted so a variation was raised.

14 March 2013 – Final Variation signed.

15 March 2013 – Confirmed site start date as 26 March 2013!

22 March 2013 – On site meeting with site manager – David.

23 March 2013 – Metricon Building Sign

26 March 2013 – SITE START! site cut started

27 March 2013 – site cut finished, sediment fence installed

28 March 2013 – retaining wall dug out, security fence put in place

2 April 2013 – retaining wall being bricked

3 April 2013 – retaining wall completed

8 April 2013 – house pegged out

9 April 2013 – footings dug out and concreted

 

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s